• Hype
  • Murai
  • Lipstiq
  • Varnam
  • Hangat
  • Autofreaks
Lowyat.NET
  • News
    • Lifestyle
    • Computing
    • Hardware
    • Internet
    • Rumours & Leaks
    • Software
  • Forums
    • Kopitiam
    • Tradezone
    • Property Talk
    • Finance & Business
    • Fast and Furious
  • Gaming
    • PC Gaming
    • Console
    • Mobile Gaming
    • Esports
  • Mobile
    • Apps
    • OS
    • Tablets
    • Phones
    • Telco
      • Celcom
      • DiGi
      • Maxis
      • Tune Talk
      • U Mobile
      • Buzzme
  • Pricelists
    • Compu-zoneUpdated
    • ViewnetUpdated
    • Sri ComputersUpdated
    • StartecUpdated
  • More
    • Artificial Intelligence
    • Automotive Tech
    • Drone
    • Enterprise
    • Entertainment
    • Fashion
    • E-Hailing
    • Wearables
    • Contact Us
No Result
View All Result
Lowyat.NET
  • News
    • Lifestyle
    • Computing
    • Hardware
    • Internet
    • Rumours & Leaks
    • Software
  • Forums
    • Kopitiam
    • Tradezone
    • Property Talk
    • Finance & Business
    • Fast and Furious
  • Gaming
    • PC Gaming
    • Console
    • Mobile Gaming
    • Esports
  • Mobile
    • Apps
    • OS
    • Tablets
    • Phones
    • Telco
      • Celcom
      • DiGi
      • Maxis
      • Tune Talk
      • U Mobile
      • Buzzme
  • Pricelists
    • Compu-zoneUpdated
    • ViewnetUpdated
    • Sri ComputersUpdated
    • StartecUpdated
  • More
    • Artificial Intelligence
    • Automotive Tech
    • Drone
    • Enterprise
    • Entertainment
    • Fashion
    • E-Hailing
    • Wearables
    • Contact Us
No Result
View All Result
Lowyat.NET
No Result
View All Result

Kelana Jaya LRT Track Replacement Work To Begin On 13 September 2026

Affected stations will start operating at 9.30 AM.

by Nurul Kamil
September 10, 2026
kelana jaya lrt line 27 new trains public transport Rapid KL PULSE app my50
248
SHARES
Share on WhatsappShare on TelegramThreads

Rapid KL has announced that it will begin track replacement work on the Kelana Jaya LRT soon. The project, which is aimed at improving the rail services, will be carried out in seven phases starting this weekend and is expected to be completed by September next year.

In a statement, the company outlined the schedule for these works. As per this statement, the first phase will involve the Taman Melati and Gombak stations, with the work being carried out on 13, 20, and 27 September.

rapid kl express bus busses evening peak hour congestion LRT stations merdeka service disruptionThen, the second phase will cover the Universiti, Kerinchi, and Abdullah Hukum stations on 15, 22, and 29 November. As for the third phase, it will affect the Dato’ Keramat, Jelatek, and Setiawangsa stations on 10, 17, and 24 January 2027. The remaining phases are as follows:

  • 14, 21, 28 March 2027 – Universiti, Kerinchi, Abdullah Hukum
  • 9, 16, 23 May 2027 – Masjid Jamek, Dang Wangi, Kampung Baru, KLCC, Ampang Park
  • 11, 18, 25 July 2027 – Taman Jaya, Universiti, Kerinchi, Abdullah Hukum
  • 12, 19, 26 September 2027 – Taman Melati, Gombak
Rapid KL Kelana Jaya LRT track replacement schedule
Image: Rapid KL

Rapid KL clarified that these efforts serve to ensure that the track infrastructure remains safe and reliable. The company’s statement went on to note that work on the longer and curved sections will require more time to complete, and may stretch until the following morning. As such, affected stations will begin operating at 9.30 AM on the scheduled days, rather than the usual 6 AM. Meanwhile, the stations not involved in the works will continue operating as usual.

Related Article Rapid KL Begins Installing Platform Safety Barriers At LRT Stations

Throughout the process, ticketing machines at the affected stations will be temporarily closed until 9.30 AM. Passengers will be able to purchase tickets at station counters. That said, Rapid KL and Touch ‘n Go product users can continue their journeys as usual.

nubia Air Photo Samples5

Other than that, a free shuttle bus service connecting the affected stops will be provided. Meanwhile, station staff, auxiliary police, and “Prasarana Troopers” volunteers will be on site to assist with passenger movement. Signage and information leaflets will also be available. The company also advises passengers to stay up to date on the track replacement work schedule and alternative routes during this time.

(Source: Rapid KL)

Filed Under kelana jaya lineLRTRapid KL
Updated 12:26 pm, Thu, 10 September 26
SendShareShareShare99Tweet62

Follow us on Instagram, Facebook, Twitter or Telegram for more updates and breaking news. 

No Result
View All Result

TRENDING THIS WEEK

  1. 1
    Gaming

    Konami Releases Original Castlevania Game For Free On Android, iOS

  2. 2
    Tablets

    Apple Code Leak Reveals iPad 12, iPad mini 8 Details

  3. 3
    Fintech

    Tencent Launches TenPayGo Payment App For Those Travelling To China

  4. 4
    Hands On

    Xiaomi 18 Pro Max Hands On: First To Rock The Snapdragon 8 Elite Extreme

  5. 5
    Telco

    BeONE Mobile Officially Launches As Maxis-Powered MVNO

NETWORK

  • Hype
  • Murai
  • Lipstiq
  • Varnam
  • Hangat
  • Autofreaks

ABOUT

  • Advertise
  • Careers
  • Privacy Statement
  • Editorial Policy
  • Terms of Use
  • Contact Us

©2026 VIJANDREN RAMADASS. ALL RIGHTS RESERVED.

No Result
View All Result
  • News
  • Forums
  • Laptops
  • Telco
  • Mobile
  • Gaming
  • Artificial Intelligence
  • Fintech
  • Cryptocurrency
  • Cyber Security
  • Hybrid Vehicles
  • Advertise with Us

©2026 VIJANDREN RAMADASS. ALL RIGHTS RESERVED.

No Result
View All Result
  • News
  • Forums
  • Laptops
  • Telco
  • Mobile
  • Gaming
  • Artificial Intelligence
  • Fintech
  • Cryptocurrency
  • Cyber Security
  • Hybrid Vehicles
  • Advertise with Us

©2026 VIJANDREN RAMADASS. ALL RIGHTS RESERVED.